Date:07/01/2009
URL: http://www.thehindubusinessline.com/2009/01/07/stories/2009010751180402.htm
Back
Cable cut: RCom gives update
New Delhi, Jan 6
Reliance Communications has informed the telecom
regulator that it has completed the repair of the cut
on FLAG under sea cable that occurred between
Alexandria (Egypt) and Palermo (Italy).
In a letter to the TRAI, RCom said, "This was completed by December 29,
2008, a day ahead of the scheduled completion date and
all customer traffic has been normalised. Sea Me We 4
and Sea Me We 3 cable systems had also reported
completion of repairs on Jan 4 and 5 respectively,
resulting in the redundant path on our global networks
fully restored to provide the required resilience and
diversity of routes to our customers." - Our Bureau
© Copyright 2000 - 2009 The Hindu Business Line | |